Project Information
Location: University of the Fraser Valley, Abbotsford, BC
Start: June 15, 2006
Completion: August 20, 2007
Budget: $11,500,000
Principles Involved:- Building Owner: University of the Fraser Valley
- Contractor: VanMar Constructors
- Architect: Raymond Letkeman Architects Inc.
Contact: Craig Toews University of the Fraser Valley 33844 King Road, Abbotsford, BC, V2S 7M7 Phone: 604-854-4576 | Fax: 604-853-2733 | Email: [email protected]
Description of Project:
- VanMar Constructors 1017 Inc. was selected as Construction Manager at Risk
- 4 storey wood frame building constructed on an underground concrete parkade
- 8000 SF Campus Bookstore on the main floor
- 204 Bed, 70,000 SF Student Residence
- Hardiplank, stucco, and masonry cladding
- 2 Ply SBS and Metal Roof
- Sanitary Lift Station for the new buildings on Campus
Team Members
- Art Van Maren (VanMar)
- Jeff Marin (VanMar)
- Jason Letkeman (Raymond Letkeman Architects Inc.)
- Craig Toews (University of the Fraser Valley)
- Jorge Candia (University of the Fraser Valley)